London, UK – Injection Waterproofing for a Piling Contractor

Project Details
Client :
Piling Contractor
Category :
Waterproofing
Location :
London, UK
Date :
June 2022
Injection Waterproofing For Piling Contractor - 1

Managing Water Ingress for Effective Waterproofing Systems

In construction, managing water ingress is crucial for ensuring the effectiveness of waterproofing systems. This project in London involved Total Specialist Maintenance (TSM) collaborating with a piling contractor who faced significant challenges related to water ingress.

Injection Waterproofing For Piling Contractor - 2
Injection Waterproofing For Piling Contractor - 5

The Challenge

The piling contractor encountered substantial water ingress through a secant piled wall, which obstructed the installation of a structural waterproof tanking system by their waterproof membrane contractor. This issue required immediate attention to facilitate the ongoing construction process and prevent delays. Key concerns included:

  • Disruption to Construction Timelines: The water ingress hindered progress, creating potential setbacks in the overall project schedule.
  • Ensuring Installation Integrity: It was essential to address the water issue promptly to allow for the effective installation of the waterproof membrane, which was critical for the structure’s long-term performance.

The Solution

TSM developed an effective solution that included several key steps:

  • Drilling: TSM created access points into the secant pile wall and the back of the wall. This step was crucial for effectively addressing the water ingress and facilitating the subsequent repair processes.
  • Resin Injection: TSM conducted resin injection works to halt water ingress and fill any voids caused by the washout of fines. A structural geopolymer injection resin was used for this purpose, ensuring a robust seal that would effectively mitigate water penetration.
Injection Waterproofing For Piling Contractor - 3
Injection Waterproofing For Piling Contractor - 4
Injection Waterproofing For Piling Contractor - 1_500wx500h

Project Management Excellence

TSM’s project management team coordinated all aspects of the solution, ensuring that the work was completed efficiently and with minimal disruption to the ongoing construction activities. Regular communication with the piling contractor and waterproof membrane contractor facilitated a collaborative approach, aligning efforts to achieve a successful outcome.

Quality Assurance and Safety

Throughout the project, TSM maintained rigorous quality assurance protocols to ensure that all work met industry standards and client expectations. Safety was prioritised at every stage, with operatives trained to adhere to best practices in construction safety.